AD Transport
Project Name: AD Transport
Project Location: Canton, MI
Year Completed: 2018
This job was done in four phases. Each phase required excavation and installing 3 inches of #3C leveling course asphalt. Concrete dolly pads and catch basins were adjusted and the entire lot was re-striped.
Services Used:
- Asphalt Excavation
- Asphalt Paving
- Rip Rap Installation with geofabric
- Concrete dolly pads
- Striping and catch basin adjust